ExplainerTransportationCalifornia3 min read

What the new $1.3 billion Hollywood Burbank Airport terminal will change for travelers

The Burbank-Glendale-Pasadena Airport Authority's $1.3B Elevate BUR terminal project is scheduled to open in October 2026 with 14 gates.

Share

Topics

Exterior view of Hollywood Burbank Airport with a curved perforated canopy and bold sign reading 'HOLLYWOOD BURBANK AIRPORT' near the entrance, cars and greenery in the foreground.

BURBANK, Calif., July 8 (Burbank News Online) — Hollywood Burbank Airport is replacing its current terminal complex with a single larger building that will keep the airport at 14 gates but move travelers into one new place for check-in, security and baggage claim.

The Burbank-Glendale-Pasadena Airport Authority is overseeing the $1.3 billion project, known as Elevate BUR. Public project timelines show the new terminal scheduled to open in October 2026, with one updated timeline setting the date at Oct. 13, 2026. Voters approved the replacement project in 2016, and construction began in January 2024. That means the airport is in the middle stage of the work: funded and under construction, but not yet operational.

What is being built?

Project descriptions say the airport is replacing its two smaller terminals with one larger terminal. The new building is expected to include a ticketing lobby, a new TSA checkpoint, baggage claim, shops and restaurants, and a new parking structure.

The terminal’s size is reported differently in project summaries, with figures ranging from about 335,000 square feet to 355,000 square feet. The gate count is not changing. The new terminal is planned to have 14 gates, the same number the airport has now.

After the new building opens, the old terminal buildings are expected to be torn down.

Who is building it?

The airport authority is using a design-build setup. In simple terms, that means one team handles both design and construction instead of splitting the work into separate contracts.

Public project listings identify Holder Construction, Pankow Builders and TEC Constructors & Engineers as part of the design-build team. Jacobs is listed as the project manager, and the architecture team includes Corgan and CannonDesign.

How far along is the project?

Progress reports have changed as construction has advanced. One update put the terminal about 32% complete in March 2025. Another said steel framing was finished and the project was about 55% complete in September 2025.

Those milestones show the work moving through the main construction phase toward the finish-out stage, when crews focus on systems, interiors and final site work.

What will change for parking and access?

One airport project summary says the new parking structure will hold 2,007 vehicles, including 400 valet spots. The same summary says the airport’s total parking supply will remain 6,637 spaces.

Another project detail places the new entrance at Winona Avenue and Hollywood Way. Airport officials have said the airport’s operating hours and the number of flights will not change.

What is still uncertain?

Public project summaries do not spell out a full funding breakdown beyond the $1.3 billion total. The exact opening date also appears in two forms: October 2026 in several reports, and Oct. 13, 2026 in an updated timeline.

Even with those details still moving, the basic plan is clear: one replacement terminal, the same 14 gates, new parking, and a project timeline that now points to a 2026 opening.